This is a story about how the U.S. military built a lavish headquarters in Afghanistan that wasnât needed, wasnât wanted and wasnât ever used at a cost to American taxpayers of at least $25 million.
From start to finish, this 64,000-square-foot mistake could easily have been avoided. Not one, not two, but three generals tried to kill it. And they were overruled, not because they were wrong, but seemingly because no one wanted to cancel a project Congress had already given them money to build.In the process, the story of â64Kâ reveals a larger truth: Once wartime spending gets rolling thereâs almost no stopping it. In Afghanistan, the reconstruction effort alone has cost $109 billion, with questionable results.
The 64K project was meant for troops due to flood the country during the temporary surge in 2010. But even under the most optimistic estimates, the project wouldnât be completed until six months after those troops would start going home.
Along the way, the state-of-the-art building, plopped in Afghanistanâs Helmand province, nearly doubled in cost and became a running joke among Marines. The Pentagon could have halted construction at many pointsâ"64K made it through five military reviews over two yearsâ"but didnât, saying it wanted the building just in case U.S. troops ended up staying. (They didnât.)
The Pentagon brass chalked up their decisions on the project to the inherent uncertainty of executing Americaâs longest war and found no wrongdoing. To them, 64Kâs beginning, middle and end âwas prudent.â
The $25-million price tag is a conservative number. The military also built roads and major utilities for the base at a cost of more than $20 million, some of it for 64K.
Ultimately, this story is but one chapter in a very thick book that few read. The Special Inspector General for Afghanistan Reconstruction routinely documents jaw-dropping waste, but garners only fleeting attention. Just like the special inspector general for Iraq did with its own reports.
With 64K, SIGAR laid bare how this kind of waste happens and called out the players by name. The following timeline is based on the inspector generalâs report, supporting documents and ProPublica interviews.
May 19, 2010: 1st General Rejects 64K. Tally: 1 âNoâ Vote.
Christened âCamp Leatherneck,â the base was fairly barren with dirt-floored tents for a few thousand Marines, but would grow sizably as President Barack Obamaâs surge of 33,000 troops arrived in Afghanistan. The Marines were taking charge of Helmand and Nimroz provinces, an area the military called Regional Command Southwest.
They were working on creating housing, a post office, four gyms, a store and nearly 11 miles of roadsâ"all the necessities of daily life at large bases, even in combat zonesâ"and commanders had recently upgraded from a tent to plywood headquarters.
But in Kabul and an ocean away, at military commands in South Carolina and Florida, plans had been underway to replace the plywood with a hulking, 64,000-square-foot facility that would dwarf its surroundings in both size and sophistication. (And also suck up considerable power from a new $14-million utilities upgrade for electrical, sewage and water that planners had decided was now required on base.) Even with the growth, Mills was skeptical he needed the headquarters.
The 64K building was a part of 2010âs massive, $482-million build-up for the surge. Although Obama had made clear the flood had an end dateâ"troops would start to withdraw in July of 2011â"the military was prepping to build way past that timeframe.
In fact, despite what Obama said publicly, the military quietly assumed troop strengths would be maintained for five years and had master plans for 10, according to Army Maj. Gen. Bryan Watson, who would later be director of engineering for U.S. forces in Afghanistan.
But, at least in the case of 64K, no one had asked the commander at Camp Leatherneck whether anyone needed or wanted a sprawling new facility larger than a football field. Marine Maj. Gen. Larry Nicholson, who was Millsà predecessor, said he not only didnât ask for it, he had no idea it was in the works.
âWe certainly needed many things in those early days at Camp Leatherneck,â Nicholson would later recall, âbut we were very pleased with [current headquarters], and frankly we had many far more pressing facility issues.â
That hadnât changed when Mills took over. He reviewed all planned projects for the next two years to evaluate ìthe relevancy of each project to the overall counter-insurgency missionî and whether the troops needed them.
The 64K building didnât make the cut. (Read Millsâ cancellation request memo here.)
June 22, 2010: 2nd and 3rd Generals Want 64K Killed. Tally: 3 âNoâ Votes.
The Marines have an adequate command headquarters, he wrote in a memo, so the project is âno longer required.â
Three generals had now come to the same conclusion: No one needed the 64K building. This was the time to stop the project.
August 2010: Three âNoâ Votes Overruled By One Superior âYesâ. 64K Moves Ahead.
The cancellation requests landed on the desk of Army Maj. Gen. Peter Vangjel, deputy commanding general of U.S. Army Central (pictured below). The command was ultimately in charge of military construction in Afghanistan.The previous month, funding for the surgeâ"including $24 million specifically ticketed for the 64K buildingâ"had been signed into law. To kill the facility now and divert the funds elsewhere, the military would have to consult Congress, a bureaucratic process called âreprogrammingâ. And no one seemed to want that.
Vangjel agreed to Millsâ requests to cancel other Leatherneck projects that hadnât been assigned money by Congress already, but not 64K. Cancelling the project, âwhich has appropriated funds, and reprogramming it for a later year is not prudent,â he wrote in a memo.
Vangjel gave no other reasons to justify spending the millions of taxpayer money.
For similar reasons, Vangjel at the same time refused to substitute the 64K building with a new request from Mills for a much smaller headquarters. Vangjel later said he was advised that a new round of approvals would delay the project too long and it might end up being too small.
But U.S. Army Central wasnât eager to get 64K going. The command wanted to âmove it to the bottom of the pile,â Vangjelâs staff member Lt. Col. Marty Norvel wrote in an email. They would like to push it âas far to the right as possibleâ on the calendar, as late as January 2012, and âensure we time this award to support other operational needs.â
SIGAR found that the correspondence âconfirm[ed] there was no immediate operational need for the 64K building.â Instead, âthe real purpose was to retain the project for some other possible use in the future.â
May 2011: Construction Begins on 64K, Even Though No One Needs It.
The military broke ground on the 64K building at an inauspicious time.The Coalition forces had already begun handing control of the country back to the Afghans and would soon start pulling troops out of the country.
On June 22, Obama announced what everyone already knew. The drawdown of forces would begin in July. Ten thousand troops would be home by the end of the year, 20,000 more would leave by the end of 2012. And by the end of 2014, the combat mission would be over. Marines, in particular, would be headed out.
At this point, the 64K building wasnât even â12 percent complete.â
It was the same story throughout Afghanistan. Construction that the military decided it needed in 2009 was just starting to come to fruition. Just like everything else in government, the projects took a long time to wind through the bureaucracy. Too long for war.
So come August, the military in Afghanistan, according to Watson, was âstill building like crazy.â
October 26, 2011: Military Axes $128 Million of Military Construction, But Not 64K.
Five months after Obama told the country troops will âcontinue coming home at a steady pace as Afghan Security forces move into the lead,â the military suddenly realized it had to, Watson said, âtake steps to get off the âbuild outâ program.âMarine Maj. Gen. John A. Toolan, the Regional Command Southwest commander at the time, canceled $128 million in military construction projects and wrote that âthe time to stop building is now.â
The 64K building wasnât on the list.
For projects already underway, Watson said, the military weighed the consequences of canceling, including âhow much was already obligated, how much could be saved after we paid the contractor termination penaltiesâ and whether the project could be used for something else.
The Pentagon also told SIGAR that at the time 64K was required to serve as the headquarters for an enduring presence at Camp Leatherneck.â But that conflicts with the recollections of other generals who said the matter was far from settled.
Watson wrote that at this time the military construction review for Marine bases was âvery contentious because there was no clear decision on whether [Leatherneck] would become an enduring base.â
And the fate of the base would remain undecided for at least another year and a half. Marine Maj. Gen. Charles Gurganus, an RC-Southwest commander, said in an interview with ProPublica that when he left in 2013 âthere were still discussions about it.â
So whether the U.S. would keep a long-term presence in Helmand was up in the air, and thousands of Marines already were going home. Yet the military continued to build a pricey, permanent headquarters facility at Leatherneckâ"just in case.
May 13, 2012: Marinesâ Mission Shrinks. But 64K Still Grows.
Once construction got rolling on 64Kâ"after Mills was goneâ"the Marines embraced it. Neither of the next two commanders, Toolan and Gurganus, attempted to downgrade the plans.Stuck with the building, the Marines modified it to their liking. From September 2011 to April 2012, they made 15 changes. Seven increased the total cost by about $1 million. And they made an assortment of pricey upgrades, spending, for example, nearly $3 million for audio and video electronics and more than $526,000 for a video teleconference suite.
All the âbells and whistlesâ came from the Marines, according to Watson. (View the full 64K cost sheet here.)
By this point, the Afghans had taken over security for all of Helmand, and the U.S. had started closing bases and sending equipment home. The Marines would soon shutter dozens of outposts.
And yet construction on 64K continued apace, seemingly without regard to the changing dynamics of the war. Stopping construction at that point would have cost more, Gurganus said. ItÃs a common dilemma with wartime contracts. Payments often are made up front and half the money can be spent before anything is built.
Though he said he âwould have done fine with a tent,â Gurganus planned to move into 64K once the building was finished.
Finally, five months later, in October, the 64K building was doneâ"but problems with the fire exits kept Marines from moving in right away. Then, in December, the Marines went for yet another change, this time moving around interior walls to accommodate a large conference table. The modification added more than $341,000 to the tab and caused more delays.
By the end of December, the Marines who poured into the country during the surge had gone homeâ"and no one had used 64K.
April 9, 2013: 64K Is Built. Marines Decide Not to Use It.
Maj. Gen. Walter Lee Miller sent an email to his bosses: He wouldnât be using the 64K building that was finished in February, but still lacked communications equipment.âI have no intent to move in,â Miller wrote. âMany reasons, we are too small...we are moving into the fighting season and it is not ready.â Any further installations to the building have been halted, he continued, to âend the money drain.â (Another $19,414 went toward workers for furniture assembly regardless.)
This confirmed, SIGAR wrote in its report, âwhat was already known back in May 2010: that the Marines at Camp Leatherneck did not require a 64K command and control facility.â
July 8, 2013: Empty, Fancy Building Attracts Attention of SIGAR.
Not surprisingly, the state-of-the-art building, empty except for the furniture still wrapped in plastic, caught the eye of SIGAR.It was âthe best constructed building I have seen in my travels to Afghanistan,â John Sopko, SIGARâs head, told then-Secretary of Defense Chuck Hagel, after he saw the wood-paneled auditorium, reclining chairs for conferences and high-end credenzas during a tour.
Officers, well aware of the joke the building had become, had taken Sopko aside while he was in Afghanistan to ensure he saw it.
Sopko later learned that the military had been scrambling to determine what to do and say about what had become a white elephant.
The Pentagon told SIGAR there had already been one investigation in May and another was underway. The first investigation had concluded that the best thing to do was to convert the building to something else, maybe a gym or a movie theater, so it wasnât a complete waste.
But Marine Gen. Joseph Dunford, who was Commander of U.S. Forces-Afghanistan and who would later be nominated as chairman of the Joint Chiefs of Staff, realized those conclusions were insufficient. The building, he wrote in his order for a new investigation, âhas the potential to draw significant attention from auditors and Congress, and raises questions as to its approval and construction.â He had this new investigation helmed by a two-star general.
Vangjel was correct in refusing the Marinesâ request to cancel the project because he knew that 64K was part of a larger âstrategic visionâ for long-term use of Camp Leatherneck, Richardson wrote in his report. The Marinesâ request for a smaller headquarters also proved that there was a need for some sort of facility.
An email exchange from Richardsonâs investigation starkly displayed the pervasive military culture of nonchalance towards costs. Although âas a taxpayer [Iâm] not happy with waste,â Navy Cmdr. Timothy Wallace wrote Richardson, given how much the military has spent on construction in the uncertain environment of Afghanistan, âif $30 million is the worst of it, thatâs probably not bad in the grand scheme of things.â
In his final report Richardson also heaped blame on the Marines who did not attempt to âreduce or prevent costsâ until three years after the cancellation request.
To bolster his finding that the building was appropriately constructed, he noted that it had progressed through the leadership of five different Marine commanders. He did not mention that three out of five had never been consulted or had deemed the project unnecessary. The first didnât know about it, the second tried to cancel it, and the fifth arrived after it was done and said he wasnât going to move in.
Richardson recommended that 64K be completely finished by adding the required communication equipment and that troops be ordered to use it as their headquarters.
This recommendation, or âviable optionâ as Richardson put it, would cost an additional $5 millionâ"more than twice the cost of just demolishing it.
Nov. 27, 2013: SIGAR Doubts Pentagon, Opens Own Investigation.
Concerned that Richardsonâs investigation was not a âthorough and candid review,â SIGAR decided to jump in.âWe were surprised that the results we saw didnât really make much sense,â Sopko said.
The military was not pleased and immediately moved to quash, or at least inhibit, SIGARâs work.
Col. Norman Allen, a staff lawyer for Dunford at the U.S. Forces-Afghanistan command, sent an email to some command staff saying heâd prefer that they âslow-rollâ SIGAR, but thought they couldnât.
In February, Allen sent another email mentioning âloyalty to the commandâ and noting that he âwould consider it inappropriateâ for people to tell âSIGAR what they think of the...investigation appointed and approved by the commander.â
Allen also wrote that he, personally, has a good deal of knowledge about the investigation, but he wasnât going to cooperate with SIGAR.
Three days later, the U.S. Forces-Afghanistan inspector generalâ"who was on those email chainsâ"sent a memo asking that âappropriate authorities intervene to cease SIGARâs evaluation of command internal business.â How the military conducted its investigation of the 64K building, he wrote, is out of SIGARâs jurisdiction.
As SIGAR discovered those documents, investigators were troubled, because as Dunfordâs legal advisor, Allen was in a position to discourage full cooperation.
SIGARâs Sopko said in an interview that he couldnât fathom how anyone would think that as an independent inspector general he couldnât look behind the scenes.
âThatâs like saying I can look at fraud, waste and abuse but I canât look at generals. Or I can look at fraud, waste and abuse, but not the reasons why [they occur],â he said.
The Pentagon stalled Sopko where it could, initially withholding from SIGAR the exhibits for the second investigation done by Richardson, for example. Then officers resisted turning over any other documents related to 64K, and Allen commented in an email that he didnât think Sopko âhad the authorityâ to force them to, and, regardless, â[we] donât think weâre working on providing him more info.â Forced by law to reply, some unclassified documents were turned over on a classified disc, requiring time-consuming procedures and limiting who could view them.
âI think they delayed this a long time,â Sopko said.
Later in the year, during a summer visit to Camp Leatherneck as SIGARâs investigation was ongoing, Sopko said he learned his military escorts had been told not to even drive by the 64K building with him.
Oct. 26, 2014: Marines Go Home Without Ever Using 64K.
The U.S. turned the 64K building over to the Afghans. It is wired for American voltage, not Afghan, and the sophisticated fire system, air conditioning and power generation system all require specialized training. Not even the Marines had anyone on base who could repair the A/C. The monthly cost to operate the building is $108,300. As such, the military predicted the building would fast fall into disrepair in Afghan hands.Employing serious understatement, one Defense Department document stated: âcertain technologies, such as those designed in the [64K building] are not as accessible to nations in this region, whether because of cost or lack of interest or requirement.â
The document said there was âno knowledgeâ that Afghanistan has the âbasic desire to maintain and operateâ the building.
May 20, 2015: Military Bungled 64K; Training Needed In Not Wasting Taxpayer Money.
SIGARâs final report blasted the military for almost every decision it made in the 64K boondoggle. The military, it charged, disregarded sound advice from three generals for seemingly no valid reason. It attempted to frustrate SIGARâs examination. And it performed a limited, ineffectual investigation of the project.SIGAR said that 64K cost the taxpayers $36 million. But its math both fails to include some costs and sweeps in too much of others. Investigators didnÃt account for the $1 million worth of modifications and the $8.3 million worth of communications equipment installed in the building, but added in the full cost of the utilities infrastructure and the nearly 11 miles of roadsâ"even though they were for the entire base that housed about 20,000 people at its peak.
The Pentagon does not consider the utilities and the roads part of the buildingâs cost, only conceding that the building, with the modifications and communication equipment, cost $25 million.
ProPublica used the $25-million figure and did not count the utilities and roads cost even though a portion of each was for 64K. Parsing the cost wasnât possible.
SIGAR found that Richardson âmismanagedâ the inquiry, failed âto carry out a fulsome investigation,â and had âno reasonable basisâ to recommend that the military complete and move into the 64K building at considerable additional cost.
âNot only was the surge long over,â the report said, âbut the U.S. had already begun to withdraw troops from Afghanistan and Camp Leatherneckâs future was in doubt.â
One startling discovery: Richardson never spoke to Vangjel, the man who denied the request to kill 64K. Richardson also didnât conduct any interviews or take sworn statements from other witnesses, instead posing questions over email, SIGARâs report said.
In an interview, Sopko said Richardsonâs explanationâ"that he didnât need to speak to Vangjel because he had sufficient information from documentationâ" âmakes no sense, and particularly not from a generalâ who should know better.
SIGAR, however, did interview Vangjel and wasnât satisfied with his answers. He told them his decision to deny the cancellation was based on a âlarger strategic planâ for Camp Leatherneck.
âHowever, [Vangjel] was unable to point to any documents, classified or unclassified, showing the existence of such a strategic plan,â SIGAR wrote.
Further, SIGAR cited concerns that Allen had, in essence, coached Vangjel on how to respond by emailing him advanced excerpts of the militaryâs own investigationâs findings.
Allen sent Vangjel an email including language from the report that said Vangjelâs decision was based on the âstrategic vision of the enduring presenceâ in Helmand.
âRather than simply asking General Vangjel why he thought it was prudent to approve the 64K building, Col. Allen appears to have provided him with the answer,â SIGAR wrote.
Mills, the general who asked to cancel 64K and had since been promoted to lieutenant general, wrote Allen that he didnât recall being consulted about the denialâ"contradicting both Vangjelâs claims and the militaryâs report. If Vangjel had talked to Marines before his decision, Mills said, he did so âwell below Flag Officer level.â
Both Allen and Vangjel disputed SIGARÃs characterization and conclusions. They each responded in writing: âI never sought to interfere with legal requirements or to coach the testimony of witnessesâ and there was âno basis to question my integrity,â Allen said.
Vangjel said he thought there were âsignificant errors throughout [SIGARâs] report and inadequate consideration of context and timing.â He also denied being âcoachedâ by Allen and repeated his assertions that there was both a need at the time for 64K and a long-term requirement.
Richardson, who is now in charge of aviation and missile readiness for the Army, didnât provide SIGAR with any comments on its report.
In its report, SIGAR recommended that Vangjel, Richardson and Allen be disciplined, and that the Pentagon do training, basically, on how not to waste taxpayer money.
The Pentagon rejected those recommendations, saying the military already has enough rules to prevent financial waste and maintaining that the decision to build the 64K building âwas prudent.â
The one recommendation that SIGAR and the Pentagon agreed on is a need to instruct service members on their legal obligation to cooperate with inspectors general.
But no one was disciplined. In fact, by November 2011, Vangjel had been promoted to lieutenant general and taken over a new post: He was the Armyâs inspector general in charge of sniffing out fraud, waste and abuse. He retired in February.
Today, the lavish project serves as the headquarters of a small Afghan regiment, according to an Afghan colonel who is a spokesman with the Ministry of Defense. Unable to make use of the high-tech âbells and whistles,â it brought its own generator and occupies only a fraction of a cavernous space meant for at least 1,200 people.
This story originally appeared on ProPublica. Itâs been republished under a Creative Commons license. And if youâre involved in reconstruction efforts in Afghanistan, you should help ProPublica Investigate.
0 Response to "EnTech: Boondoggle HQ: The $25 Million Building in Afghanistan Nobody Needed"
Post a Comment